Estimated Timeline
0 of 7 stations approved0% complete
Plan Check Status
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Townes Chris.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Howard Brett.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Hayes Janice.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Walls Mark.
Bottleneck Watch: Sidewalk & Street
Sidewalk & Street is the longest-running active review station on this project.
Key Milestones
May 2006
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2016
Permit Filed
New construction permit filed with DBI
Sep 2016
Permit Issued
Construction can begin
Sep 2020
Construction Complete
Certificate of occupancy issued