San Francisco / Bayview Hunters Point / 888 La Salle Av

888 La Salle Av

34-unit 4-story residential project aka address

Permit Issued — Under Construction34 UnitsAB 2011 Ministerial$9.9M Est. Cost
Permit Filed
Mar 2016
Active Review Since
Mar 2016
Review Stations
0 of 5
stations approved
Project Status
Issued
Estimated Timeline

Permit Issued

September 2017

Permit issued on September 12, 2017. Project moved into construction phase.

Actual permit issuance date from DBI records
0 of 5 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Walls Mark.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Chin Jeff.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Szu-Whitney Monica.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Key Milestones
Mar 2016
Permit Filed
New construction permit filed with DBI
Mar 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2017
Permit Issued
Construction can begin
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.