Estimated Timeline
0 of 5 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Howard Brett.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Cheung Janice.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Aug 2016
Permit Filed
New construction permit filed with DBI
Aug 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2017
Permit Issued
Construction can begin
May 2019
Construction Complete
Certificate of occupancy issued