San Francisco / Outer Richmond / 2224 Clement St

2224 Clement St

12-unit 4-story residential project to erect 4 stories, no basement, type 1 & 5a, 12 units residential unit with retail & parking.

Construction Complete12 UnitsAB 2011 Ministerial$3.6M Est. Cost
Permit Filed
Nov 2016
Active Review Since
Nov 2016
Review Stations
0 of 9
stations approved
Project Status
Complete
Estimated Timeline

Permit Issued

January 2018

Permit issued on January 23, 2018. Project moved into construction phase.

Actual permit issuance date from DBI records
0 of 9 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Kirby Alexandra.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
In Review
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Tan (Peter) Jia Jian.
In Review
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Chen Min.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Chung Diana.
In Review
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Tan (Peter) Jia Jian.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Nov 2016
Permit Filed
New construction permit filed with DBI
Nov 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2018
Permit Issued
Construction can begin
Apr 2020
Construction Complete
Certificate of occupancy issued