Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Townes Chris.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Kwok Stephen.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Hayes Janice.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
May 2017
Permit Filed
New construction permit filed with DBI
May 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2017
Permit Issued
Construction can begin
Jan 2021
Construction Complete
Certificate of occupancy issued