San Francisco / Marina / 2444 Lombard St

2444 Lombard St

43-unit 4-story residential project to erect 4 stories, no basement, type v-a over i-a, 2 townhouse & 41 residential units with commercial office mixed use building(r-3,r-2,b,s-2) ** maher: dis...

Construction Complete43 UnitsAB 2011 Ministerial$10.0M Est. Cost
Permit Filed
Dec 2017
Active Review Since
Dec 2017
Review Stations
0 of 7
stations approved
Project Status
Complete
Estimated Timeline

Permit Issued

October 2018

Permit issued on October 03, 2018. Project moved into construction phase.

Actual permit issuance date from DBI records
0 of 7 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: May Christopher.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Liang Karen.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Debella Al.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Yu Eric.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Szu-Whitney Monica.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Ossai Joseph.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Dec 2017
Permit Filed
New construction permit filed with DBI
Dec 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2018
Permit Issued
Construction can begin
May 2020
Construction Complete
Certificate of occupancy issued
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.