Estimated Timeline
0 of 5 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on May 30, 2018. 1 round(s) of review. Reviewer: Zee Howard.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Bottleneck Watch: Building Code
Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.
Key Milestones
Apr 2018
Permit Filed
New construction permit filed with DBI
Apr 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.